# BESS Investment Analysis — v2.13 · Digital (DA) · As of October 2026

Text version of the PDF "BESS Investment Analysis v2.13 EN Digital" (two pages). Where this text and the PDF differ, the PDF prevails. Figures are described in words. Source and contact: bess.appstam.com

## Finding · Regulation: reference and two weighted cases

**Whether the commitment holds is decided at the ballot box — a breach costs you ~€32m, largely independent of your base case.**
If the commitment falls, we weight the hard breach at 25 %.

**Figure 1 (described):** A reference line runs straight from 2026 to 2045: "Exemption (§ 118 EnWG) continues (reference)". From year 5 (2030) [3] two cases branch below it: "Draft rate if the commitment falls (~€7/kW·a) · 75 %" [2] (thin line, ~€2.6m less than the exemption) and "Full grid charge if the commitment falls (~€70/kW·a) · 25 %" (dashed line). The bracket from the reference to the full grid charge reads "~€32m NPV difference (paired per path)".

If the commitment falls from year 5, the draft rate applies in three quarters of the paths; in one quarter, the full grid charge. Whether it falls, we do not weight.

Fig. 1 — Two cases from year 5 against the commitment as reference. Below means loss against the commitment; gaps are not to scale. Breach = counterfactual stress test, not a forecast. Year 1 = 2026; cases modelled from 1 Jan 2030 (year 5), and after the 2029 federal election.

### Why now: The commitment can be breached — and the breach is permanent.

- **Today's cost** — Your bank prices this risk in today — debt sizing runs off the downside case: now, not only if the breach occurs. Diffuse regulatory risk costs you return either way.
- **Mechanism** — Capital is committed on the basis of a state commitment — and the commitment changes after the capital is sunk; a breach acts forward, applying only from the cut-off onwards.
- **Consequence** — ~€32m against the commitment if the full grid charge comes — weighted at one quarter (25 %). A basis for decisions, not a point estimate — board-ready before FID.

### Reference asset (illustrative)

| | |
|---|---|
| 50 MW · 200 MWh | 4-hour system, front-of-meter / grid-scale |
| Arbitrage + FCR | FCR set as a conservative lower bound, not co-optimised |
| Day-ahead, SMARD 10/2025–07/2026 | 15-min; intraday analysis in print only |
| 20 years (2026–2045) | year 1 = 2026 |
| Exemption years 1–4 | § 118 EnWG, grandfathered (FID before 2027) |
| From year 5, if the commitment falls: | 75 % draft rate · 25 % full charge |
| 1,000 paths, seed-paired | all cases on identical market draws |
| NPV pre-tax, WACC stochastic | mean 6.5 %, range 4–10 % |

Data: SMARD.de (BNetzA, CC BY 4.0), 15-min day-ahead — details p. 2.

## Methodology · Evidence · Contact

**What the model does: empirical market data instead of static assumptions.**
Monte Carlo, 1,000 paths on empirical 15-min market prices. Each path valued under each regulatory case, identical market draws. NPV pre-tax; the difference per path isolates the regulatory effect. Dispatch is optimised with perfect foresight (TRC) — a theoretical upper bound, not a forecast.

### Reference and hard breach, same paths

**Figure 2 (described):** Two density curves on one axis: "Full grid charge (~€70/kW·a)" [1] on the left (dashed outline), "Exemption continues (reference)" [3] on the right; a zero mark on the axis. Above the two curves: "~€32m difference per path · half of all paths €29–35m".
Schematic density of the 246 paired paths in which the hard breach occurs (kernel-smoothed); each path valued under the exemption and under the full grid charge. The draft-rate case (~€2.6m below the exemption, Fig. 1) is not shown.

Fig. 2 — Both curves show the same paths, valued under the continued exemption (right) and under the full grid charge (left). NPV pre-tax, TRC upper bound, see methodology. Illustrative calculation on the 50 MW / 200 MWh reference asset — project-specific analysis on your data.

[1] Breach parameter: full HV grid charge; current HV grid-charge sheets ~€50–90/kW·a + €15–30/MWh; 70 = upper mid-range.
[2] Draft rate: under the AgNeS draft (BNetzA, GBK-25-01-1#3), storage pays the generators' capacity-based charge (tenor 10.1 s. 2; no energy charge, reasoning paras. 406/410), recalculated yearly (tenor 9.2); the draft's reasoning indicates €4–7/kW·a (para. 50). Applied here as the mild case if the exemption falls despite grandfathering.
[3] Year 1 = 2026, FID before 2027: exempt under § 118 EnWG, grandfathered under the AgNeS draft (tenor 17.5). Reference: the exemption continues. Cases from 1 Jan 2030 (year 5), after the 2029 federal election: the draft rate (75 %) or the full HV grid charge (25 %). Whether the commitment falls is not weighted.
[4] This edition is deliberately conservative, based on day-ahead prices (licensing). The intraday analysis (ID3) is available in print only for licensing reasons — talk to us.

### Your number.

Your project, with or without grandfathering: key data is enough — we calculate your figure.
Scope: front-of-meter / grid-scale (arbitrage + FCR), one bidding zone per asset.

Sorin Pascu · sorin.pascu@appstam.com · appstam.com · +49 151 412 408 58 · bess.appstam.com/en

Sorin Pascu · Appstam Consulting GmbH · Berlin
Data: SMARD.de (BNetzA), CC BY 4.0 · v2.13, 10/2026 — distributions and hero figure recomputed against the exemption as reference (grandfathering).